Job Order Costing
Medium Practice Test
Medium Practice Test
Click the “Check Your Answer” box below each question to reveal the correct answer and explanation.
1. Work in process inventory is credited when
b. manufactured goods are completed
c. manufactured goods are sold
d. raw materials are moved to the production line
Answer
2. Finished goods inventory is credited when
b. manufactured goods are completed
c. finished goods are sold
d. raw materials are moved to the production line
Answer
3. The use of indirect materials is recorded as an increase in
b. supplies expense
c. manufacturing overhead
d. raw materials
Answer
4. Which of the following would not be an appropriate activity base for a manufacturer that is not automated?
b. direct labor dollars
c. machine hours
d. total material dollars
Answer
5. A manufacturing company applies manufacturing overhead at a rate of 50% of direct labor dollars incurred. For a job that shows $3,000 manufacturing overhead applied, direct labor dollars incurred was
b. $1,500
c. $3,000
d. $6,000
Answer
D.
Use the formula Direct labor $ x 50% = Manufacturing O/H applied
? x 50% = 3,000 and ? is 6,000
6. Machine hours used to estimated the predetermined overhead rate were 50,000, actual machine hours used were 46,000 and overhead was under applied by $8,000. Budgeted total manufacturing overhead for the period was
b. $ 94,000
c. $100,000
d. $200,000
Answer
7. An amount of over or under applied manufacturing overhead that is not significant should be
b. added to or subtracted from cost of goods sold
c. allocated to work in process, finished goods, and cost of goods sold
d. left in the manufacturing overhead account
Answer
8. When overhead is under applied it indicates that
b. estimated overhead dollars were different than actual overhead dollars
c. estimated overhead activity was different than actual overhead activity
d. either b. or c. or both
Answer
9. A debit to work in process occurs when
b. actual manufacturing overhead is paid
c. manufacturing overhead is applied to the cost of production
d. indirect material is used
Answer
10. The cost of one completed job is calculated
b. direct material + direct labor + actual manufacturing overhead
c. direct costs + actual manufacturing overhead + beginning WIP – ending WIP
d. indirect costs + direct costs
Answer
11. Record the following transactions that occurred at the manufacturing company during the month of January. At the beginning of the year, the company estimated they would incur $900,000 and use 75,000 total annual direct labor hours.
b. raw materials were issued to production, $194,000
c. salespersons were paid salary, $29,000
d. incurred salaries and wages at the manufacturing facility, direct $89,000 for 7,500 hours and indirect $34,000
e. other factory manufacturing overhead incurred and paid, $62,000
f. utilities that incurred at the factory, $11,000
g. prepaid insurance that was used, corporate, $8,000
h. depreciation on the factory equipment, $17,000
i. 95% of product costs were completed (do not consider under or over applied manufacturing overhead)
j. products that cost $325,000 were sold for $500,000
Answer
a. raw materials were purchased on account, $236,000
Raw materials $236,000
Accounts Payable $236,000
b. raw materials were issued to production, $194,000
Work in Process $194,000
Raw materials $194,000
c. salespersons were paid salary, $29,000
Selling expense – salary $29,000
Cash $29,000
d. incurred salaries and wages at the manufacturing facility, direct $89,000 for 7,500 hours and indirect $34,000
Work in Process $89,000
Manufacturing Overhead $34,000
Salaries Payable $123,000
e. other factory manufacturing overhead incurred and paid, $62,000
Manufacturing Overhead $62,000
Cash $62,000
f. utilities that incurred at the factory, $11,000
Manufacturing Overhead $11,000
Cash $11,000
g. prepaid insurance that was used, corporate, $8,000
Insurance expense – G&A $8,000
Prepaid Insurance $8,000
h. depreciation on the factory equipment, $17,000
Manufacturing overhead $17,000
Accumulated depreciation $17,000
i. 95% of product costs were completed (do not consider over or under applied)
1st – Apply overhead so that all product costs are in WIP.
$900,000 / 75,000 = $12 per hour x 7,500 actual hours = $90,000
Work in Process $90,000
Manufacturing overhead $90,000
2nd – Total all product costs for the period:
direct material used 194,000
direct labor used 89,000
manufacturing overhead applied 90,000
total product costs 373,000
x 95% complete . 95
cost of finished products 354,350
Finished Goods $354,350
Work In Process $354,350
j. products that cost $325,000 were sold for $500,000
Cost of goods sold $325,000
Finished Goods $325,000
Cash $500,000
Sales $500,000
You were not asked to do this, but you should also 0 out the manufacturing overhead account and make the costs in WIP equal to actual and not estimated.
Actual 124,000 (34 + 62 + 11 + 17)
-Applied 90,000
Under applied 34,000
This is significant and would be allocated and debited to WIP, FG, and CGS based on the balances in the accounts. You would credit manufacturing overhead for 34,000 to get the manufacturing overhead account to 0.
12. A manufacturing company that produces product using mostly automation had the following for the current period.
Actual manufacturing overhead costs incurred $345,976
Budgeted manufacturing overhead costs $400,000
Budgeted direct labor costs $ 90,000
Actual direct labor costs $ 86,542
Budgeted direct labor hours 8,182
Actual direct labor hours 7,902
Budgeted machine related costs $172,000
Actual machine related costs $185,347
Budgeted machine hours 20,000
Actual machine hours 20,945
The company uses machine hours as the activity base for allocating overhead to products. Over and under applied overhead is recorded to cost of goods sold. Record all necessary journal entries related to overhead for the period.
Answer
Ignore all information related to direct labor costs and direct labor hours as this is not relevant. The company used machine hours not labor hours. Calculate the predetermined overhead rate per machine hour.
Budgeted MOH costs $400,000 = $20 per machine hour
Budgeted machine hours 20,000
Then apply manufacturing overhead – add costs to WIP
Actual machine hours used x rate per machine hour
20,945 x $20 = 418,900
Work in Process $418,900
Manufacturing overhead $418,900
Record actual manufacturing overhead costs incurred.
Manufacturing overhead $345,976
Cash $345,976
Do not record the machine related costs, they are already included in total manufacturing overhead incurred
Zero out the manufacturing overhead account.
Applied 418,900
Over applied 72,924
too much cost put in the product so you have to reduce the cost
Manufacturing overhead $72,924
13. A manufacturing company uses a job costing system and recorded the following activity for the month.
Job # | Direct Materials | Direct Labor |
34 | $305 | $560 |
35 | $210 | $965 |
36 | $690 | $315 |
The company estimated that total manufacturing overhead incurred would be $150,000 and total material dollars used would be $75,000. Job # 34 was completed and delivered to the customer. The other two jobs are completed and not delivered to the customer.
Calculate the following:
a. the total product costs recorded for each of the 3 jobs during the month
b. the cost of goods sold for the month
c. the ending balance in work in process for the month
d. the ending balance in finished goods
e. record the journal entries for the costs moving through the production line
Answer
a. Total product costs consist of direct material, direct labor, and manufacturing overhead applied. Apply overhead and get the total for all 3 jobs
Calculate a predetermined overhead rate:
Total budgeted O/H $ / total activity
$150,000 / $75,000 = 200% of direct material costs
Overhead applied is Material $ x 2.00
#34 #35 #36
DM 305 210 690
DL 560 965 315
OH applied 610 420 1,380
Total cost 1,475 1,595 2,385
b. Job #34 was completed and delivered to the customer. The cost of this job is also cost of goods sold. $1,475
c. WIP at the end of the period is 0 since there are no jobs current unfinished.
d. The cost of finished goods is the cost of jobs #35 and #36 – $3,980
e. Adding product costs for direct material and direct labor is recorded as
Work in process – #34 865
Work in process – #35 1175
Work In process – #36 1005
Raw materials 1,205
Salaries payable 1,840
Apply the manufacturing overhead:
Work in process – #34 610
Work in process – #35 420
Work In process – #36 1,380
Manufacturing overhead 2,410
Move the cost of completed products
Finished Goods 5,455
Work in process – #34 1,475
Work in process – #35 1,595
Work In process – #36 2,385
Record the cost of the goods delivered to the customer
Cost of goods sold 1,475
Finished goods 1,475