Variable Cost Variance Analysis
Easy Practice Test
Introduction to Accounting
Easy Practice Test
Click the “Check Your Answer” box below each question to reveal the correct answer and explanation.
a. actual production costs
b. sales price
c. expected average production costs
d. management sales targets
Answer
a. machine hours
b. units produced
c. labor hours
d. all of the above
Answer
a. materials quantity variance
b. labor price variance
c. variable overhead efficiency variance
d. all of the above
Answer
a. materials price variance
b. materials quantity variance
c. labor rate variance
d. variable overhead budget variance
Answer
a. actual hours worked and estimated hours worked
b. actual hours worked and estimated hours to make the actual products
c. actual cost per hour and estimated cost per hour
d. a supervisor’s rate of pay and a direct labor workers rate of pay
Answer
a. actual hours worked and estimated hours worked
b. actual hours worked and estimated hours to make the actual products
c. actual cost per hour and estimated cost per hour
d. a supervisor’s rate of pay and a direct labor workers rate of pay
Answer
a. material actually used was higher than the material expected to be used for production
b. the standard material used was lower than the actual material
c. the price paid for each was higher than expected
d. material used was higher than what was used in the prior year
Answer
a. production manager
b. research and development engineer
c. purchasing manager
d. sales manager
Answer
a. labor efficiency variance
b. overhead efficiency variance
c. overhead budget variance
d. material use variance
Answer
Standard | |
Materials | 1 pound at $7 per pound |
Labor | 1.5 hours at $12 per hour |
Variable Overhead | $10 per labor hour |
Fixed Overhead | $3.50 per labor hour |
Budgeted production for the year | 6,000 units |
Actual | |
Materials Purchased | 5,200 pounds for $36,720 |
Materials Used | 5,100 pounds |
Direct Labor | 7,000 hours at $86,100 |
Variable Overhead | $56,170 |
Fixed Overhead | $19,680 |
Units Produced | 5,200 |
Answer
AQ x AP AQ x SP AQ x SP SQ x SP (purchased) Purchased Used Used 5,200 x ? 5,200 x $7 5,100 x $7 5,200 x 1 x $7 =$36,720 = $36,400 = $35,700 = $36,400 Variance $320U $700 F price quantity
Labor:
AQ x AP AQ x SP SQ x SP 7,000 x ? 7,000 x $12 5,200 x 1.5 x $12 = $86,100 = $84,000 = $ 93,600 Variance $2,100 U $9,600 F rate efficiency
Variable Overhead:
AQ x AP AQ x SP SQ x SP
$56,170 7,000 x $10 5,200 x 1.5 x $10
= $70,000 = $78,000
Variance $ 13,830 F $8,000 F
spending efficiency
Important to notice:
Use labor hour information for the quantity for overhead because the overhead rates are based on labor hours.
The SQ “standard allowed” is the actual units made x the standard that each one takes.
The fixed overhead budget must be calculated since it is not given.
Actual for the current year:
Purchases of raw materials 25,000 yards at $13yd
Raw materials used 22,000 yards
Direct labor 12,000 hours at $10
Variable O/H costs $68,150
Units produced: 8,000
Standards per unit of product:
Raw Materials: 1.8 yards at $14 per yard
Direct Labor: 0.90 hours at $11.50 per hour
Variable O/H: $7 per direct labor hour
Answer
Material:
AQ x AP AQ x SP AQ x SP SQ x SP Purchased Purchased Used Used 25,000 x $13 25,000 x $14 22,000 x $14 8,000 x 1.8 x $14 = $325,000 = $350,000 = $308,000 = $201,600 Variance $25,000 F $106,400 U price Quantity
Labor:
AQ x AP AQ x SP SQ x SP 12,000 x $10 12,000 x $11.50 8,000 x .9 x $11.50 = $120,000 = $138,000 = $82,800 Variance $18,000 F $ 55,200 U rate efficiency
Variable Overhead:
AQ x AP AQ x SP SQ x SP $68,150 12,000 x $7 8,000 x .9 x $7 = $84,000 = $50,400 Variance $15,850 F $33,600 U
Important to notice:
Do not be concerned if the variances are big numbers, just work the calculation correctly.
Use labor hour information for variable overhead because the variable overhead rate is per labor hour.
The SQ is the actual units made x the standard that each one takes.
Material uses two different AQ x SP, one for used and one for purchased.
No fixed overhead information is provided so this variance is not done.
12. The following information is available for the company:
Standard Cost Card:
DM 6 feet at $2 per foot
DL 5 hours at $3 per hour
VOH $1 per hour
Information related to actual production:
Units Produced: 20,000 Materials Purchased: 130,000 feet at $2.10 per foot Materials Used: 110,000 feet Direct Labor 115,000 hours at $3.25 per hour Variable OH $112,500
Answer
Material:
AQ x AP AQ x SP AQ x SP SQ x SP Purchased Purchased Used Used 130,000 x $2.10 130,000 x $2 110,000 x $2 20,000 x 6 x $2 = $273,000 = $260,000 = $220,000 = $240,000 Variance $13,000 U $20,000 F price quantity
Labor:
AQ x AP AQ x SP SQ x SP 115,000 x $3.25 115,000 x $3 20,000 x 5 x $3 = $ 373,750 = $345,000 = $300,000 Variance $28,750 U $45,000 U rate efficiency
Variable Overhead:
AQ x AP AQ x SP SQ x SP $112,500 115,000 x $1 20,000 x 5 x $1 = $115,000 = $100,000 Variance $ 2,500 F $15,000 U spending efficiency