Variable Cost Variance Analysis
Hard Practice Test
Introduction to Accounting
Hard Practice Test
Click the “Check Your Answer” box below each question to reveal the correct answer and explanation.
a. more materials were purchased than used
b. more materials were used than purchased
c. the actual cost of materials was less than standard cost
d. the actual usage of materials was less than the standard
Answer
a. have materials that were easy to work with
b. hired labor that was not up to quality standards
c. purchased and used material that was higher quality than standard
d. paid more per hour than was expected
Answer
a. the difference between the budget allowed for the actual units made and the actual variable overhead costs incurred
b. unlimited usage of variable overhead materials
c. the difference in the budgeted amount of time that should have been spent to make the product and the budgeted hours expected to be used
d. the difference in actual hours used in production and the standard hours expected for what was actually produced.
Answer
a. material quantity and labor efficiency
b. material quantity and labor rate
c. labor rate and overhead budget
d. labor efficiency and overhead efficiency
Answer
a. workers were more experienced than planned for
b. workers were less experienced than planned for
c. the purchasing manager bought higher quality material than planned for
d. workers that were hired were under-qualified to perform the job
Answer
Direct materials 10 yards ?? Direct labor 2 hours $12 per hour Variable Manuf. O/H 1.5 hours $ 8 per hour
The total cost for one is $55.50. What is the cost of material per yard?
a. $4.20
b. $1.35
c. $0.45
d. $1.95
Answer
Actual direct labor hours 9,000 hours Actual labor rate $8 per hour Standard labor hours allowed 8,000 hours Direct labor rate variance $6,750 unfavorable Direct labor efficiency variance $7,250 unfavorable
What is the standard rate per hour for labor?
a. $7.25
b. $6.95
c. $9.99
d. $8.59
Answer
a. make changes that hopefully will result in fixed costs being significantly lower
b. determine what can be done to reduce variable product costs
c. decide which manager should be fired
d. prepare a budgeted income statement
Answer
Standard Total Standard Cost Direct Materials 4 pounds $6.00 Direct Labor .5 hours $5.00 Variable O/H .5 hours $2.00 Fixed O/H .5 hours $8.00
During the year the company produced 3,000 units.
8,900 pounds were purchased at a cost of $13,729
Inventory increased by 360 pounds this year
1,265 direct labor hours were worked at a cost of $11,467
Actual variable manufacturing overhead incurred was $4,157
Actual fixed manufacturing overhead incurred was $18,702
Budgeted production was 3,200 units
Compute all of the following and write the amount as favorable or unfavorable
Answer
AQ x AP AQ x SP AQ x SP SQ x SP
Purchased Purchased Used Used
$13,729 8,900 x $1.50 8,540 x $1.50 3,000 x 4 x $1.50
= $13,350 = $12,810 = $18,000
Variance $379 U $5,190 F
price quantity
Labor:
AQ x AP AQ x SP SQ x SP
$11,467 1,265 x $10 3,000 x 0.5 x $10
= $12,650 = $15,000
Variance $1,183 F $2,350 F
rate efficiency
Variable Overhead:
AQ x AP AQ x SP SQ x SP
$4,157 1,265 x $4 3,000 x .5 x $4
= $5,060 = $6,000
Variance $903 F $940 F
spending efficiency
Important to notice:
The rate/ cost per is not given and is calculated by dividing the total standard cost by the standard quantity.
Material used was calculated by material purchased less inventory increase.
When inventory increases, not as much is used.
Actual cost of direct materials purchased and used $75,492 Total materials variance $12,817 Unfavorable Total materials price variance $6,325 unfavorable Standard cost per yard of materials $5 Standard cost per labor hour $8 Actual direct labor hours worked 7,600 Labor efficiency variance $5,600 unfavorable Standard direct labor hours per unit 1.5 Total labor variance $1,000 favorable
What were the total units produced during the month?
What is the standard yards for material?
What is the actual material cost per yard?
What is the actual direct labor cost per hour?
What is the labor rate variance?
Answer
What is the standard yards for material? 3
What is the actual material cost per yard? $5.457 rounded
What is the actual direct labor cost per hour? $7.1316 rounded
What is the labor rate variance? $6,600 F
Material:
AQ x AP AQ x SP AQ x SP SQ x SP Purchased Purchased Used Used ? plug ? plug ? plug 13,833.4 x $5.457 13,833.4 x $5 4,600 x 3 x $5 = $75,492 = $69,167 plug = $75,492 = $69,000 plug Variance $6,325 U $6,492 U price quantity Total Variance $12,817 U
Labor:
AQ x AP AQ x SP SQ x SP plug 7,600 x $7.1316 7,600 x $8 4,600 x 1.5 x $8 = $ 54,200 plug = $ 60,800 calc = $ 55,200 plug Variance $6,600 F $5,600 U rate efficiency
Total Variance $1,000 F
Important to notice:
Put the problem information in the formula first.
Notice that you have more info for labor, so plug and calculate what you were not given.
Doing the labor will give you units made, use this in the material SQ.
Work backwards, calculating and plugging until you have the entire equation worked.
Actual
|
Standard
|
|
Raw materials purchased, 10,500 each |
$23,100
|
$21,000
|
Raw materials used |
10,900
|
10,000
|
Direct labor payroll |
$122,100
|
$120,000
|
Direct labor hours worked |
14,800
|
15,000
|
Total Manufacturing overhead incurred/applied |
$182,500
|
$184,500
|
Budgeted fixed overhead |
|
$46,750
|
Variable overhead actual $ and stnd. rate per hour |
$127,500
|
$3.00
|
Manufacturing overhead is applied based on 42,500 annual machine hours.
Three hours of machine time is required for each direct labor hour.
Compute all variable cost variances and state favorable or unfavorable
Answer
AQ x AP AQ x SP AQ x SP SQ x SP Purchased Purchased Used (used) 10,500 x $ 2 10,900 x $ 2 10,000 x $2 = $23,100 = $21,000 = $21,800 = $20,000 Variance $2,100 U $1,800 U price quantity
Labor:
AQ x AP AQ x SP SQ x SP 14,800 x $8 15,000 x $8 = $122,100 = $118,400 = $120,000 Variance $3,700 U $1,600 F rate efficiency
Variable Overhead:
AQ x AP AQ x SP SQ x SP $ 127,500 14,800 x 3x $3 15,000 x 3 x $3 = $133,200 = $135,000 Variance $5,700 F $1,800 F spending efficiency
Important to notice:
Overhead is applied based on machine hours and it takes 3 machine hours for 1 direct
labor hour.
So, to get the standard machine hours you must always multiply the direct labor hours by 3.
If overhead was based on direct labor hours you would not multiply by 3, and you would use the direct labor hour standard.
The standard represents the SQ, the standard allowed to produce actual units.